Government of Gujarat 

HOME :: URBAN TRANSPORT :: BRTS

Bus Rapid Transit System


Four cities of Gujarat namely Ahmedabad, Surat, Rajkot and Vadodara have been identified for the BRT initiatives

 

BRTS

 

Key aspects of the mission are as follows :

  • AHMEDABAD – A total corridor length of 88 km was planned, out of which 45 km is operational. The total no. of bus terminus is 67 and 112 buses are operating serving with daily ridership of 125,000
  • SURAT – A total corridor length of 100 km was planned to be completed in two phases with 30 km in the first phase and 70 km in the second phase. The total number of bus terminus is 200
  • RAJKOT – A total corridor length of 29 km was planned out of which 11 km has been completed. The total number of bus terminus is 35
  • VADODARA – Currently the detailed feasibility report is being prepared

Achievements :

  • Best Intelligent Transport System Award, GoI 2011
  • Best Sustainable Transport in the World Award, 2010
  • Best Mass Transit Project Award, 2009